Comment: Found out Capitalization matters in the "

...

Zen Section
id873734300

Mapping for Date

Because the date formatting can vary from one resource to another, ILLiad has the ability to parse the date correctly from the resource record to the ILLiad request from by editing the OpenURL Mapping table in the Customization Manager. The following configuration will parse out the year from the referring record into the ILLiad request as a 4-digit value.

  1. In the Customization Manager, navigate to Web Interface | OpenURL | OpenURLMapping
  2. Find the record for PhotoJournalYear and double-click to open the editing window.
  3. Add DATE|yyyy to the ILLiadValue field. (Capitalization matters here!)
  4. Save the change by clicking into another field and then click the Save button.



Info

The OpenURL mapping can be configured to parse other Date and Time formats.